Price River Water Improvement District - Wastewater Treatment Plant Rehabilitation Project

This project will be to rehabilitate the existing wastewater treatment plant. There will be a significant amount of mechanical work - replacing aging valves and piping, upgrading the existing HVAC system, burner equipment and digester piping. Alder Construction will also replace the existing digester lids to complete this project scope.

Project Details

Project Location: Price, Utah
Project Start: May 2011
Project Completion: est. October 2011
Contract Size: $ 1,359,000
Site Superintendent: Tony Siaperas
Structural Superintendent:
Project Manager: Val Martin
Owner: Price River Water Improvement District
Engineer: Water Works Engineers