Completed Projects List

Below is a partial list of some of the many projects Alder Construction has successfully completed.
Click on the thumbnail image to see more details

St George
St George Headworks Renovation Project - (Completed August, 2011)
St George, Utah

The City of St George needed to update their aging headworks equipment and since Alder Construction built this original plant, we were excited to get back onsite. The project consisted of some site work, including replacing and adding some new concrete pads to accommodate the new equipment, replacing the worn out bar screens with new JWC screens, installing a new washer compactor and associated electrical work. MORE......

Dannon
Dannon Yogurt Pre-Treatment Facility - (Completed June, 2011)
West Jordan, Utah

Dannon Yogurt needed to build a new wastewater pre-treatment facility to replace their aging, out of date facility that was not able to keep up with Dannon's current waste and their projected growth. As their timeline to complete this project was extremely short, they used a design/build delivery method to complete this project in six months. MORE........

Quail Creek
Quail Creek Water Treatment Plant - (Completed May, 2011)
Hurricane, Utah

Alder Construction has worked at the Quail Creek WTP many times and returned in 2010 to begin construction of a new 10 million gallon water reservoir to help Washington County keep up with the growing population. MORE.....

Central Weber
Central Weber Wastewater Treatment Plant Upgrade - (Completed April, 2011)
Ogden, Utah

Alder recently finished work at the Central Weber Wastewater Treatment Plant. Our contract included construction of two primary clarifiers, four secondary clarifiers, a RAS/WAS pump station, raw sludge pump station and primary splitter box. MORE.....

Springvillee
Springville Wastewater Treatment Plant - (Completed October, 2009)
Springville, Utah

Designed by Aqua Engineers, the upgrade of the existing wastewater facility for the City of Springville increased the plant BOD capacity from 12,000# to 21,000# and the hydraulic capacity was increased from 5.2 to 7.7 million gallons per day. The existing plant was required to remain in operation while Alder forces constructed several new basins and structures and modified several others. These include the renovation of an existing basin to create a new 7000 sf,... MORE......

Magna
Barton Wellfield - (Completed June, 2009)
Magna, Utah

The Barton Wellfield project involved the completion of a new 6.0 MGD electro-dialysis reversal (EDR) water treatment plant with new feed tank and finished water blending tank. This project also included upgrading the existing Magna Wastewater facility located a few blocks away. On this site we added a new headworks building and BIOBROx facility. Alder was very pleased to be involved with the construction . . . MORE........

Weber South
Weber South Water Treatment Plant - (Completed November, 2009)
Ogden, Utah

The Weber South Water Treatment Plant needed to upgrade its aging facility and increase its capacity from 26 million gallons per day of treated water to 32 million gallons per day. This project included constructing a new filter building which also houses several new offices and a laboratory. Alder Construction also built a new chemical building, . . MORE.....

Clifton
Clifton Regional Wastewater Treatment Plant
(Completed June, 2009)
Clifton, Colorado
SV-TD
South Valley Water Reclamation Facility
Thermal Drying Facility
(Completed December, 2007)
West Jordan, Utah
SV4C
South Valley Water Reclamation Facility Project 4C
(Completed February, 2007)
West Jordan, Utah
Havasu
Lake Havasu City Wastewater Treatment Plant Expansion
(Completed September, 2007)
Lake Havasu City, Arizona
Rock Springs
Rock Springs Wastewater Treatment Plant
(Completed November, 2007)
Rock Springs, Wyoming
LC
Little Cottonwood Water Treatment Plant - Onsite Improvements Project #LC020
(Completed October, 2007)
Sandy, Utah
Burley
City of Burley Wastewater Treatment Plant Upgrade
(Completed July, 2007)
Burley, Idaho
City Creek
City Creek Water Treatment Plant Upgrade
(Completed May, 2006)
Salt Lake City, Utah
LC
Little Cottonwood WTP Expansion Project
Completed June, 2006)
Sandy, Utah
Quail
Quail Creek WTP - 40MGD Expansion
(Completed December, 2005)
Hurricane, Utah
SV 4B
South Valley WRF Project 4B
(Completed July, 2004)
West Jordan, Utah
Neely
Neely Water Reclamation Plant
(Completed August, 2004)
Gilbert, Arizona