CITY CREEK WATER TREATMENT PLANT UPGRADE - SALT LAKE CITY, UTAH

This $8.3 million project got underway in late 2004 and included the construction of a new administration building, new chemical building, new raw water control and piping. It also included improvements to the existing flocculation basins, filters and washwater tanks. All construction was successfully completed on time in February 2006.

Project Manager - Shane Harris
Site Superintendent - Warren Sterner

Owner - Salt Lake City Corporation - http://www.slcgov.com/Utilities/ud_watershed.htm
Engineer - Brown & Caldwell - www.brownandcaldwell.com